A 105-megawatt wind farm enters commercial operation in Finland

OX2 says its Honkakangas wind farm began commercial operation in early November, about three months ahead of schedule. The 16-turbine project adds renewable generating capacity in Halsua, Finland.

Finland has another operating source of renewable electricity. OX2 announced on November 19 that its Honkakangas wind farm in Halsua had entered commercial operation earlier in the month, around three months ahead of its original timetable.

The project’s 16 turbines have a combined capacity of about 105 megawatts. OX2 puts annual generation at roughly 360 gigawatt-hours. That is an expected yearly output, rather than a measured full year of production; actual generation will depend on wind conditions and availability.

The first electricity reached the grid in July. Construction followed an investment decision in spring 2025, and OX2 will retain ownership and manage the completed wind farm.

The milestone adds working renewable capacity that can support electrification. The announcement does not provide a measured figure for avoided greenhouse gas emissions.