Juniper completes a 108.5 MWp solar component for a hybrid power project
Juniper Green Energy says its ETA Five subsidiary commissioned the full solar component of a wind-solar project on November 19. The addition brings 108.5 megawatts of peak solar capacity into operation.
Juniper Green Energy says its ETA Five subsidiary commissioned the entire 108.5-megawatt-peak solar component of a wind-solar hybrid project on November 19. The milestone adds working solar capacity to a project designed to combine wind and sunlight.
The company’s stock-exchange filing identifies the wider project as a 75-megawatt wind-solar hybrid scheme, with a power purchase agreement with Maharashtra State Electricity Distribution Company Limited.
The two ratings describe different parts of the project. The 108.5 MWp figure is the solar equipment’s peak capacity; it should not be added to the wider project’s 75-megawatt rating or read as annual electricity generation.
Combining solar and wind can spread renewable production across different conditions and hours. The filing confirms this solar commissioning milestone, but does not provide measured annual output or quantify avoided emissions.