Naturgy has brought a new battery system into operation at Tabernas, in Spain’s Almería province. It is connected to the company’s Tabernas I and II solar plants, which have operated since 2022.
The two lithium-ion installations have a combined power rating of 42.4 megawatts and storage capacity of 89.4 megawatt-hours. Megawatts describe how quickly power can be delivered; megawatt-hours describe the amount of energy the batteries can hold.
That storage allows some solar electricity to be saved and released when needed, rather than requiring it all to be used as it is generated. Naturgy says the installation cost €20.4 million.
The November 24 announcement confirms an operating project. It does not report measured annual emissions savings.